Bellbird Estate 45 large residential blocks subdivision

Kerroc completed the investigation for the DA proposal including surveying. geotechnical studies environmental review studies, Bush Fire management and completion of design all works which were constructed to approval standards and specification.

Works on site included but limited.
  • Clearing, and Earthworks
  • Grading and leveling to compaction level 1
  • Construct 300m Main Road widening and improvements to council specification
  • Construct 500m internally roads of 8m wide
  • Construct intersection to Main road
  • Easements for services and future works
  • Construction of 981m of 100mm watermain, 350 m of 150mm watermain, associated valves and fittings
  • Construction 1346m of 150mm sewer including 26 maintenance shafts of various depths (1m – 3m) and six concrete manholes varying to 1.5m to 4m deep
  • Construction of 1500m of stormwater of various sizes 375- 600mm including stormwater pits and lintels and the dam / retention basis
  • Install complex conduits for services and Future works
  • Construction of Kerb and guttering, 700 meters of internal Footpaths
  • Management of Electrical supply, Power poles underground service, Substation, cabling, and streetlights
  • Installation of NBN services and cabling
  • Connection of all services into the stakeholders’ infrastructure
  • Plan and Manage shutdowns for watermain and sewer connection and power outage
  • Landscaping, surveying, and conveyancing
  • Kerroc received approval and acceptance of works from all stakeholders in relation to the service constructed