Lucas / Hunter Water Corporation
Applied various work methodologies for construction due to the diverse terrain from rolling hills to congested infrastructure and utilities work zones.
Fabrication of the Bend on site allowing progress to occur and precision.
Construction in various classification of soils form extreme hardness of rock in Dugong to sandy soils in Fisherman / Anna bay.
Construction in different environments from isolation (Dungog) to urban, residential areas (fisherman/Anna bay).
Distance between projects.
Resolving issues with a design on the run, successfully completing Cut-in and installation of the DICL Y piece to the DN 1350 during night works within restricted time limits, without disruption to network.
Successful planning, management, and achievement of completing the water mains connections crossover. No 3 major cut-ins of various sizes including the installation of Flowmeters simultaneously within restricted hours without any safety, environmental incidents, or disruption to the network.