Projects

Kurri Kurri Waste Water Treatment Works

This contract involves the upgrade of the existing biosolids handling facilities at Kurri Kurri Waste Water Treatment Works (WWTW). The works was Design, Development, Construct and install

The main works include but are not limited to the following
  • Extension to Digester Cells
  • New conveyors Systems
  • New switch room building
  • New Electrical Switchboard, controls and upgrade and modification to existing switch room
  • New diffuser aeration system
  • Pneumatic airline. Vales and Blowers
  • Installation of Client supply Gravity Deck and Centrifuge
  • Associated, design, design development, excavations, piling, foundations, trenching, concreting, saw cutting, reinforcement, associated, steel works, valves, fittings and Pipework
  • Roadworks—construct Access road to new switch room building, Reconstruction & sealing of existing site access roads
  • Removal and disposal of redundant equipment
  • Testing and commissioning
Extension of the digester tanks
  • The existing 3 cell aerobic digester at Kurri Kurri was augmented by the construction of 2 new cells and a new buffer tank
  • Dismantle and dispose of the existing diffused aeration system the existing aeration system was completely replaced to provide aeration to the new 5 cell digester
  • Modifications to the access platform over Cell 1 and associated work
  • Install stairs and handrails to provide access to the area between the old digester holding cells and the new ones

 

Digested Waste Activated Sludge (DWAS) pumping facilities
  • Installation of the new DWAS pumps, pipe work, valves, access stairs, access steps, the monorail, electrical cable trays, cables (where possible), lighting, GPO etc. in and around the DWAS pump station
  • construction of the DWAS rising main to the centrifuges

 

Aeration system
  • The existing aeration system was completely replaced and a new aeration to the new 5 cell digester was provided
  • Design and construct the diffused aeration system including air pipework, diffusers. diffuser pipework, valves etc for the new digester cells
  • Dismantle and dispose of the existing diffused aeration system

 

Blower Room
  • Modifying the blower room to suit the new blowers
  • The installation of the new air pipe from the plant room to the biosolids building
  • Connection of the new blowers’ pipelines and the new DWAS
  • Connection of air supply to all pneumatic valves
  • Sludge Thickening device
  • Disassemble the existing gravity Deck
  • Installation of the New Gravity Drainage Deck (GDD) and Centrifuge
  • Installing the support frame for the inlet box for the GDD
  • Modifying and provide new drainage bunds, new/existing floor grating to suit the new GDD arrangement
  • Install the WAS inlet pipe work to suit the new GDD
Centrifuge Dewatering System
  • Disassemble and remove the existing centrifuge and make modifications to suit and install the new centrifuge
  • Provided miscellaneous valves and connections as required
  • Modifying and provide new drainage bunds, new/existing floor grating to suit the new arrangement

 

Conveyor system
  • Design & install new conveyor system (conveys sludge from the centrifuge) provide and install a screw conveyor solids inlet chute to suit the new centrifuge for discharge to the fixed screw conveyor

 

Switch room and electrical
  • Construct new Switch room with floor plan of 16 m x 6 m (internal)
  • Provision of all electrical equipment in a new fire-rated switch room containing the new MCC switchboard, harmonic power correction equipment, PLC, UPS, and VSDs to cater for the plant upgrade
  • Power, control, instrumentation, and communication cabling including electrical pits, aboveground/underground conduits and cable ladders
  • Connections of power, control and instrumentation wiring to new equipment and instruments
  • Switchboard, field control panels and field instrument panels
  • Relocate the DWAS and instrument electrical panels
  • Connections of power, control and instrumentation wiring to new equipment and instruments
  • Terminations of wiring in switchboards, field instrument panels, field control panels, etc
  • Integration of vendor packaged plant including GDD polymer dosing system (and centrifuge polymer dosing system)
  • Modifications to the existing main switchboard and associated control and instrumentation for Plant upgrades
  • Connection of power supply to the blowers
  • Connection of bulk cabling to instrumentation
Challenges

Planning & rescheduling of the work program around the issues to achieve progress and prevent interruption to the treatment plant.

Overcoming Numerous latent conditions e.g. mechanical, geotechnical, electrical, structure, redundant services (buried sedimentation tanks, structures pipework. cables) and delays in client supplies.

Underground cabling throughout the site including 11kv feed to transformer.

High noise levels in Blower room and Dewatering building.

Contact with sewage and gases.

Handling and Disposal of Biologically Contaminated Materials.

Are you looking for Construction and Industrial Experts?